TL;DR
SoftBank Group reported a ¥1.12 trillion ($7.0 billion) net loss for July-September 2026, reversing a profit a year earlier. A major factor was a ¥597.2 billion loss tied to changes in power-equipment procurement after a subsidiary had paid $9.5 billion in advance for equipment and factory capacity. SoftBank says $6.6 billion remains allocated to equipment and it may receive conditional rebates on future purchases.
SoftBank Group reported a ¥1,115.3 billion ($7.0 billion) net loss for the July-September quarter on November 10, 2026, with a ¥597.2 billion ($3.73 billion) loss tied to changes in power-equipment procurement for planned U.S. AI data centers. The charge followed $9.5 billion in advance payments by a subsidiary for power-generation equipment and reserved factory capacity, illustrating the financial risks of locking in infrastructure before project requirements are settled.
SoftBank said the subsidiary, Silver Bands 7 (SB7), paid ¥1.5 trillion, or about $9.48 billion through September 30, under manufacturing-capacity reservations, equipment purchase contracts and other arrangements. The commitments supported U.S. AI data center projects, including the PORTS-Pike Technology Campus in Ohio. SoftBank described the advance purchases as a way to secure equipment amid expected shortages.
After SB7 revised its procurement strategy to reflect changing project requirements, SoftBank recorded $2.9 billion in losses on non-refundable advances for equipment removed from its plans and another $0.9 billion for contract modifications and settlements. The company said cash payments related to the latter amount are expected from the third quarter onward. It said $6.6 billion of the advance payments remains allocated to equipment for PORTS-Pike and other projects.
SoftBank said it could receive rebates of up to $2.1 billion over 10 years on future equipment purchases, subject to conditions. It did not record those rebates as an asset because the amount could not be determined. The company also said it expects to recoup its investment through project financing. The quarter’s net loss compares with ¥2,502.2 billion in net income in the same period a year earlier; sales rose to ¥2,215.4 billion from ¥1,916.5 billion.
SoftBank’s Quarterly Loss Centers on AI Power Equipment
A change in power-equipment plans drove a major charge, showing the financial risk of securing infrastructure before data center requirements are settled.
Power Commitments Carry Financial Risk
The report shows how power equipment can become a costly constraint in AI data center development, alongside access to chips and sites. SoftBank paid to secure equipment and factory capacity ahead of final project specifications; when plans changed, some payments could not be recovered. The charge turns a supply-chain problem into a direct hit to quarterly earnings.
The exposure also matters beyond SoftBank’s income statement. The company is developing and financing data center capacity, while OpenAI is identified in the source material as a long-term tenant and a major SoftBank investment. Nvidia is described there as guaranteeing part of the tenant’s lease obligations. Those links create financial interdependence, but the reported equipment charge alone does not establish that any other party has incurred a loss or that a project will be delayed.
For businesses seeking AI computing capacity, the episode is a reminder that announced data center plans depend on power infrastructure and procurement schedules, not only on server orders. SoftBank’s disclosure does not quantify the effect on available computing capacity, customer prices or project timelines.
Products Worth Considering

Jackery Explorer 300 Portable Power Station with 40W Solar Panel

Anker SOLIX C300 DC Portable Power Station with 60W Solar Panel, 288Wh, 300W

Apple MacBook Air 13.6-inch Laptop with M5 Chip, 16GB Memory, 512GB SSD, Midnight
As an affiliate, we earn on qualifying purchases.
How the Procurement Charge Arose
SoftBank’s fiscal year runs from April through March, so the reported second quarter covers July through September 2026. The company was profitable in its first fiscal quarter, reporting ¥347.3 billion in net income, before recording the second-quarter loss. For the six months through September, the net loss attributable to owners was ¥768.0 billion.
The power-equipment charge was one part of a broader earnings swing. SoftBank reported finance costs of ¥461.9 billion in the quarter, compared with ¥174.7 billion a year earlier, and other losses of ¥669.9 billion. Revenue increased, but losses and costs below the sales line outweighed that growth. SoftBank’s report says its financial statements are an English translation of the Japanese original and had not been reviewed by auditors.
At a Tokyo briefing, Chief Financial Officer Yoshimitsu Goto said, according to Reuters, that intense competition for energy supply and power equipment prompted purchases before long-term specifications were final. SoftBank’s investor presentation said SB7 changed its plans as the requirements of existing and planned projects evolved. The company has not disclosed the suppliers or specific equipment involved.
“made bridge investments in advance to secure power generation equipment in anticipation of shortages”
— SoftBank Group investor presentation
Unanswered Questions on Equipment
SoftBank has not identified which equipment was ordered, which suppliers were involved, or which purchases were cancelled. It has not provided project-by-project details showing whether revised procurement will change construction schedules or the amount of data center capacity ultimately delivered.
The potential rebates of up to $2.1 billion are conditional and spread across future purchases over as long as 10 years; the company did not book them because their value could not be determined. The report also does not specify how much of the remaining $6.6 billion in advances corresponds to each project or when the equipment will be delivered. SoftBank’s expectation that project financing will help recover the investment is a company forecast, not a completed recovery.
Future Payments and Project Financing
SoftBank said cash payments for contract modifications and settlements are expected from the third quarter onward. Investors will be watching subsequent results for those costs, whether any conditional rebates become measurable, and whether the company can arrange the project financing it says will help recoup the investment.
Further company disclosures may clarify how the revised equipment plan affects PORTS-Pike and other U.S. data center projects. Until SoftBank gives details on suppliers, delivery schedules and project financing, the practical effect on construction and future computing capacity remains unknown.
Key Questions
Why did SoftBank report a $7 billion quarterly loss?
SoftBank reported a ¥1,115.3 billion ($7.0 billion) net loss for July-September 2026. A major factor was a ¥597.2 billion loss related to revised power-equipment procurement, alongside higher finance costs and other losses.
How much did SoftBank pay in advance for power equipment?
SoftBank said its subsidiary SB7 had paid ¥1.5 trillion, about $9.48 billion, through September 30, 2026, for power-generation equipment and reserved manufacturing capacity.
What part of the advance payments was written off?
SoftBank recorded $2.9 billion in losses on non-refundable advances for equipment removed from the revised procurement plans, plus $0.9 billion for contract modifications and settlements.
Could SoftBank recover some of the loss?
The company said it may receive rebates of up to $2.1 billion on future equipment purchases over 10 years, subject to conditions. It did not book the rebates as an asset because the amount could not be determined, and said it expects project financing to help recoup its investment.
What is still unknown about the data center plans?
SoftBank has not named the suppliers or specific equipment involved, or said how the procurement changes affect project schedules and expected capacity. Details on the future rebates and project financing are also not yet available.